XINGYI Project Team:Brunei customer 4000sqm granite polishing assistant
Xingyi 2 projects managers provide technical guidance for concrete and granite polishing in Brunei projects. Our Brunei customer is very satisfied with the floor effect.
The concrete grinding process:
Step 1:Metal diamond pads 30#60#120#;
Step 2:Resin diamond pads 50#100#;
Step 3:Surface cleaning&repairing with concrete repairing adhesive(had better wait for 12-24 hours after the adhesive);
Step 4:Resin diamond pads 100#;
Step 5:Concrete densifier for concrete hardening(had better wait for 24 hours after the concrete densifier);
Step 6:Resin diamond pads 200#400#800#;
Step 7:Concrete protective sealer with high speed burnisher and high speed buffing pads 1500# and 3000#
The granite polishing process:
Step 1: Finished goods protection;
Step 2:Cutting the joints;
Step 3:Spraying stone sealer;
Step 4:Repairing the joints;
Step5:Rough grinding and fine polishing with resin diamond pads 50#100#200#400#800#1500#3000#;
Step 6:Crystallization with granite polishing compound.